Date Finished Summer 2018
Tags Groundworks, Earth Moving & Civil Engineering
This project was on the A39 between Bideford and Bude and the main contractor was Willmott Dixon.
The site was on a slope so we undertook the earthworks cut/fill exercise first to give the size two level platforms, one for the carpark and one for Academy and playing fields. Once this was complete, we carried out the foundation works, drainage, drainage storage tanks, playgrounds, playing fileds and external finishes.
The bad weather throughout the winter months of this project made it very challenging but despite the bad weather the project was a success and finished as planned in the summer of 2018.