Date Finished 2023
Tags Earth Moving & Civil Engineering, Tipping Facilities
This project was for TDA. The site is circa 13 acres and the intention from the client is to eventually cover the area with a solar farm to feed the local hospital, but the area was to uneven to be able to do this in its current state.
Circa 22,000m3 was imported from a donor site to use to fill and level off the ground. Before the material was imported, we had already installed a new access and had stripped the topsoil. Once the material had been imported and spread/levelled, the topsoil was re-spread over the area.
The project finished on time as planned and the client was pleased with the quality of work and finished outcome.